• Download mobile app
17 Mar 2025, Edition - 3534, Monday

Trending Now

  • It is because of the Dravidians that the country’s regressive gangs have not been able to rise up – M.K.Stalin, Chief Minister
  • According to RBI statistics, there were 10.8 million credit cards in circulation by December 2024, almost double the number of 5.53 million, 5 years ago.
  • Saying that people are afraid of the Mullaperiyar dam breaking, sounds like a ‘comic’ story”- Supreme Court Justice Rishikesh Roy
  • Bumrah wins ICC Test Cricketer of the Year 2024 award.

Coimbatore

Normal rail, road traffic resumes on Madukkarai Road

Covai Post Network

Share

Normal rail and road traffic resumed today on the Madukkarai-Palakkad Road, as the replacement of girders at the road under-bridge was completed.

Trains were delayed and road traffic was diverted yesterday while the steel girders at the bridge at the Madukkarai Railway Station yard on the city outskirts were being replaced by the Palakkad Division of Southern Railway.

The works have been completed ahead of schedule as the fourth and fifth concrete slabs have also been placed, completing the entire replacement of steel girders of the bridge.

Consequently, normal rail and road traffic resumed today.